Dixie from Birch Run Road to Junction.

This portion also includes the Roundabout at Curtis and Dixie.

The current plan is to adjust the traffic shift on Dixie at Curtis Wednesday next week to the opposite side. The traffic shift is needed to complete the westerly half of the roundabout. A temporary traffic signal will be set up trading North and South Bound traffic.

Curtis Road will be closed in both directions when this change occurs.

This portion of the project is still on schedule to be completed before Labor Day.

Dixie from Willard to Birch Run Road

This portion was bid out in Late June with Pyramid Paving being the prime asphalt contractor. A traffic signal will be added at the Burt Road intersection and center left turn lanes will be added for this intersection. Construction for this portion of road will likely begin in late August. The roadwork will likely be complete by November with the signal installation likely in the winter.

If you have any questions,
Dan Armentrout
Director of Engineering